Draft Torbay - Elleker Rail Trail Development Plan

Home | TCG | Catchment | Project Background | Publications | Help | News | Events | Caring | Community | Contacts


[Back] [Index][Next]

SECTION 7 - COST ESTIMATES

7.1 Typical Construction Rates

In considering the costs set out below reference should also be made to the multitude of benefits of trails set out earlier in this report. These benefits should be taken into account by the entire community when determining whether development of a trail within the former railway corridor will proceed.

Obviously some areas/segments of the trail will vary in terms of what elements of the construction process will be required. For example, some segments of the former railway corridor will require fencing (or re-fencing) one or both sides of the corridor (to satisfy adjoining landowners who require it), while in other segments of the corridor little or no fencing will be required. Much of the fencing is already in place anyway. Similarly, clearing of vegetation from the trail corridor, and removal of rubbish and weeds will be much simpler in some segments, and much more difficult in others.

  • Fencing: * see Note 1
    • New: $7.00/metre
  • Trail construction (see process below). Construction includes vegetation clearing/grading/shaping trail alignment (inc. materials, machinery & labour): $15-20/metre
  • Bridges: * see Note 2
    • Re-decking * ($1,000/m)
    • Safety railings: $70/metre
  • Boardwalks (3.0m wide; no handrails): $900/m
  • Trailhead: $5,000 - $10,000 (gravelling of parking area; trailhead signage and information, map, code of conduct, etc); interpretive panel; picnic table; bike parking; perhaps a composting toilet, etc) - depends on extent of existing development
  • Weed / rubbish removal: $1/m
  • Revegetation/screening: $0.50/m
  • Drainage: $0.50/metre (where required, such as in cuttings)
  • Engineers Assessment: $1000/bridge

(Note: all distances are linear metres)

7.2 The Trail Construction Process

The following construction technique applies to the actual conversion of the sometimes overgrown railway formation to a well graded, compacted gravel surface, suitable for walking, riding off-road bicycles and horse riding.

The major issue involved in developing the trail, from a construction point of view, is the clearing of the trail corridor through the thickly vegetated regrowth on the railway formation. The process that follows may be confronting to many in the community, as it describes a process using heavy machinery to clear a swathe through the vegetated corridor. The clearing at first may seem excessive, but following construction will soften as edges close in, leaf litter falls and side-vegetation grows back. The use of a small bulldozer is the most efficient - and cheapest - method for clearing the trail corridor to permit construction of the trail.

An option may be to use more hand tools and smaller machinery, which will take more time, cost more money and result in a need for more active and on-going maintenance. The photo on this page illustrates the trail corridor of the Denmark- Nornalup Heritage Rail Trail - constructed through vegetation very similar to the vegetated corridor along Lower Denmark Road. The end result of that trail construction process was a trail approximately 2.5 - 3 metres wide, in a trail corridor of around 4 metres wide. It is a pleasant, intimate experience.

Step 1 - Use small bulldozer to travel along formation to knock down any trees and all substantial vegetation growing on the formation (a trail corridor width of 3.5 - 4.0 metres wide). Bulldozer is to clear all vegetation from the trail corridor. It is assumed dozer can perform task to accomplish 2km per hour and make 1 pass along formation. All vegetation is to be removed from the rail-trail corridor and transported off-site to an authorised dump location.

Step 2 - Use front-end loader with grab bucket to travel along formation to rake up any sleepers remaining on the formation. (It is evident that most sleepers have previously been removed from the formation). Sleepers are to be grabbed in bundles and dumped to side of formation for later collection and removal). It is assumed loader can perform task to accomplish 2km per hour.

Step 3 - Use skid-steer loader, with forks, to push sleepers and all vegetation removed from formation into piles, and then later to lift on to truck for removal from site. Skid-steer loader can also be used to tidy up edges of formation ready for grading. It is assumed skid-steer loader can perform task to accomplish 4km per hour.

Step 4 - Use truck to transport vegetation and sleepers removed from formation to rubbish tip. It is assumed truck will be utilised at rate of 2 hours per kilometre.

Step 5 - Truck in required gravel for re-surfacing of the formation (where required). Imported gravel should be certified dieback free. Dump gravel in stockpiles (at each road/driveway crossing) or, where and when possible, use trucks to distribute imported gravel along trail route. Use skid-steer loader to distribute gravel from stockpiles along trail.

Step 6 - Use grader to travel along formation to grade any remaining gravel from both sides back onto formation. Grader to spread dumped gravel along trail. Grade one side first, then other, and finally a third pass to flatten and crown the gravel. It is assumed grader can perform task to accomplish 3km per hour, and make 3 passes along formation.

Step 7 - Use compacting road roller (with water tanker if being done in dry weather conditions) to compact and form up the trail surface. 3 runs along gravel probably necessary to create crowned trail surface, free of gravel bunds at edge. It is assumed roller can perform task to accomplish 5km per hour, and make 3 passes along formation.

7.3 Section and Interpretation Costs

Section 1: Elleker Hall to Lower Denmark Road crossing (east) (1,000m)
Trailhead: Elleker Hall:

Install interpretive panel [map panel] on wall of hall on veranda)


See separate table
Install 'promotional' signage (double-sided) on the Lower Denmark Road, opposite Hassell St (pointing in to Elleker trailhead).$250 ea plus installation600
Install trail directional marker in car park1120
Gravel path construction: trailhead to bridge over Marbellup Brook185m2,775
Install small culvert at low point on trail (near bridge)
700
Install extra fill and compact, at road edge east side of bridge
500
Install trail directional marker on eastern side of bridge1120
FencingNone required0
Construct 50m red asphalt path between bridge and Grasmere Rd50m @ $150/m7,500
Road crossing: Elleker-Grasmere Rd

Use painted "Shared Path" and "Give Way" markings on path. (Note: due to current configuration of intersection, Council should consider kerbing this intersection).


200
Install trail directional marker on western side of Elleker-Grasmere Rd crossing1120
Install 'trail crossing' signs on Lower Denmark Rd (x2) and on Elleker-Grasmere Rd2 @ $100ea plus installation300
Construct 60m red asphalt path on southern verge of Lower Denmark Rd between Elleker-Grasmere Rd and Brassey St.60m @ $150/mxx9,000x
Install road delineator posts between shoulder of road and shared path (every 10 metres) - between Elleker-Grasmere Rd and Brassey St.6600
Install trail directional marker opposite Brassey St1120
Road crossing: Lower Denmark Rd.

Use painted markings on path on south side. Install "Give Way" sign on post on north side.


310
Construct 100m red asphalt path on southern verge of Lower Denmark Rd between Brassey St and driveway to Elleker General Store.100m @ $150/m15,000
Install road delineator posts between shoulder of road and shared path (every 10 metres) - between Brassey St and driveway.101,000
Install "Cyclists/Pedestrians on road" warning sign on Brassey St1 @ $100ea plus installation150
Install trail directional marker at right angle bend in Brassey St1120
Note: this plan suggests use of the original railway formation between Brassey St and Marbellup Rd. 270 metres of clearing the formation, and trail construction, etc, will be required. (This has been included in cost estimates). An option is for the existing road (Brassey St) to be used all the way to Marbellup Road - with no cost.270m4,050
Road crossing:
Marbellup Road. Install "Give Way" signs on posts both sides of road.
2 @ $110ea220
Install trail directional markers on Marbellup Road2240
Install 'trail crossing' signs on Marbellup Road 50m either side of trail crossing2 @ $100ea plus installation300
Install culverts either side of Marbellup Road at trail crossing - and gravel fill over21,400
Clear vegetation &/or grade trail alignment (ie. trail construction and surfacing) 170m of original formation between Marbellup Road and Lower Denmark Rd170m2,550
Bridges: new decking and/or re-construction:

   - bridge 17.5m7,500
   - bridge 27.5m7,500
Bridges: safety railings:

   - bridge 17.5m x 21,050
   - bridge 27.5m x 21,050
Install "Road Ahead" sign 50m from Lower Denmark Rd crossing1 @ $110ea110
Road crossing:
Lower Denmark Rd (east). Install "Give Way" sign on post on north side of road.
2 @ $110ea220
Install trail directional markers both sides Lower Denmark Rd2240
Request Main Roads WA to relocate 80/110kph speed limit signs 100m west of current location
100
Install 'trail crossing' signs on Lower Denmark Rd 100m either side of trail crossing2 @ $100ea plus installation300
Interpretive panels
See separate table
Weed and rubbish removal
1,000
Re-vegetation/screening
n/a
Bridge certification by engineer
2,000
Sub-total
$69,065
Contingency & Project Management 15%
$10,360
Sub-total
$79,425
10% GST
$7,942
Total (incl. 10% GST)
$87,367



Section 2: Lower Denmark Road crossing (east) to Wilgie Road (3,880m)
Road crossing: Lower Denmark Rd (east).
Install "Give Way" sign on post on south side of road.
1 @ $110ea110
Install culvert (or small bridge) on south side of Lower Denmark Rd at trail crossing - and gravel fill over.
700
Install management access gate, chicane and cavaletti gate at commencement of this section of rail-trail (near Lower Denmark Rd)
2,800
Install "Road Ahead" sign 50m from Lower Denmark Rd crossing1 @ $110ea110
Clear vegetation &/or grade trail alignment (ie. trail construction and surfacing): Lower Denmark Rd (east) to Wilgie Rd3,700m55,500
Fill 'connection' to original formation through lowlying ground - over 40 metres40m x 1.0m deep1,000
Fencing of corridorNone required0
Construct small bridges or boardwalks over creeks, water courses and drainage lines (where timber culverts have been removed): see plan for locations

   - 'bridge' 36m5,400
   - 'bridge 4'3m2,700
   - 'bridge' 53m2,700
   - 'bridge' 65m4,500
   - 'bridge' 75m4,500
Install 'Give Way' signage on trail at 8 driveway crossings: see plan for locations. [Note: a gate and fencing system has also been allowed for at these driveway crossovers - see below].16 @ $110ea1,760
Install management access gates, chicanes and cavaletti gates each side of 8 driveway crossings1644,800
Install trail directional markers at each driveway crossing8960
Fill 'connection' from original formation through low-lying ground to Wilgie Rd - over 50 metres50m x 0.5m1,000
Install "Road Ahead" sign 50m from junction with Wilgie Rd1 @ $110ea110
Road 'crossing': Wilgie Rd.
Install "Give Way" sign on post on east side of road.
1 @ $110ea110
Install trail directional marker at junction with Wilgie Rd1120
Install management access gate, chicane and cavaletti gate at end of this section of rail-trail (Wilgie Rd)
2,800
Interpretive panels
See separate table
Weed and rubbish removal
3,700
Re-vegetation/screeningNone required0
Sub-total
$135,380
Contingency & Project Management 15%
$20,307
Sub-total
$155,687
10% GST
$15,569
Total (incl. 10% GST)
$171,256



Section 3: Wilgie Road (to gate) (1,350m)
Clearing vegetation &/or grading trail alignment (ie. trail construction and surfacing)Nil required0
FencingNil required0
Road crossing: Wilgie Rd.
Install "Cyclists / Pedestrians / Horses on road" warning sign at approach to junction with trail.
1 @ $100ea plus installation150
Install "Cyclists / Pedestrians / Horses on road" signs (double sided) at 3 locations along road.3 @ $100ea plus installation450
Request Main Roads WA to modify speed limit on Wilgie Rd to 40kph, and install speed limit signs (or "Shared Zone" signs) - see photo page 423 @ $100ea plus installation450
Construct localised road widenings or pull-off bays (where road is not within cutting or on embankment) - to enable vehicles to pass each other, and vehicles to pass trail users
2,000
Install trail directional markers at side road junctions3360
Install trail directional markers at proposed management access gate1360
Interpretive panels
See separate table
Poison weed and rubbish removal
2,000
Re-vegetation/screeningNone required0
Sub-total
$5,770
Contingency & Project Management 15%
$866
Sub-total
$6,636
10% GST
$664
Total (incl. 10% GST)
$7,300



Section 4: Wilgie Road (gate) to Lower Denmark Road crossing (west) (1,520m)
Install management access gate, chicane and cavaletti gate at western end of formed section of Wilgie Rd
2,800
Erect 15m fencing and second gate to provide a double entry gate system (for farm vehicles)
1,200
Clearing vegetation &/or grading trail alignment (ie. trail construction and surfacing)1,380m13,800
Fencing - to bring existing fences closer to formation to allow adjoining landowners to use unneeded land within railway corridor. New fencing to include 'cattle crossings' gating system (see Note 1)Allowance for 2,500m plus cattle crossings20,000
Bridges: re-construction

   - bridge 810m10,000
   - bridge 9 (boardwalk, with no handrails)5m4,500
Bridges: safety railings

   - bridge 810m x 21,400
   - bridge 9n/a0
Install trail directional marker at bridge 81120
Re-vegetation/screening - plant screen planting near Wilson residence to offset vegetation cleared in trail construction process1.728ha (@ $3/m2)51,840
Erect fencing around revegetated areaAllow for 400m2,800
Install management access gate, chicane and cavaletti gate at western end of leased section of corridor
2,800
Install trail directional marker at management access gate1120
Install management access gate, chicane and cavaletti gate at fence line
2,800
Install trail directional marker at power lines easement1120
Fill trail alignment between formation and Wilson access road, along power lines easement (105m x 3m x 0.5m)
2,100
Install trail directional marker at Wilson access road1120
Install "Road Ahead" sign 50m from junction with Lower Denmark Rd.1 @ $110ea110
Install trail directional marker on east side of Lower Denmark Rd1120
Road crossing: Lower Denmark Rd.
Install "Give Way" sign on post on east side of road.
1 @ $110ea110
Install 'trail crossing' signs on Lower Denmark Rd 100m either side of trail crossing2 @ $100ea plus installation300
Interpretive panels
See separate table
Bridge certification by engineer
2,000
Sub-total
$119,160
Contingency & Project Management 15%
$17,874
Sub-total
$137,034
10% GST
$13,703
Total (incl. 10% GST)
$150,737



Section 5: Lower Denmark Road crossing (west) to Torbay Hall (990m)
Road crossing: Lower Denmark Rd.
Install "Give Way" sign on post on west side of road.
1 @ $110ea110
Install trail directional marker on west side of Lower Denmark Rd1120
Install "Road Ahead" sign 50m from junction with Lower Denmark Rd.1 @ $110ea110
Install trail directional markers (directing cyclists and horse riders to use wide gravel track, and walkers to use existing Torbay Nature Trail)1150
Fill holes in gravel track &/or grade trail alignment for mountain bikes and horses (existing track)990m1,000
Install "Cyclists / Pedestrians / Horses on road" signs (double sided) at 3 locations along road.3 @ $100ea plus installation450
Install trail directional markers along wide gravel track (4 needed)4480
Install trail directional markers along Torbay Nature Trail (2 needed)2240
Install 'trail crossing' signs on gravel track near Torbay Hall (for Torbay Nature Trail road crossing)2 @ $100ea plus installation300
Install "Give Way" sign on posts on both sides of road crossing on Torbay Nature Trail.1 @ $110ea110
Interpretive panels
See separate table
Trailhead: Torbay Hall:
Install picnic table; install new interpretive information (incl. rail-trail map panel) in existing shelter (see separate table). Note: community to decide on access to toilets and access to running water.

2,000
Maintenance to existing Torbay Nature Trail (cutting protruding branches; cutting overhanging branches; removing fallen branches; upgrading of trail surface)
1,000
Bird hide modification: relocate entire structure close to water and off trail route (because of dangerous roof corner) - or - make good repairs to dangerous corner. Lower the viewing slot so users can sit and observe the wetland. Install interpretive panels (bird identification panels).
2,000
Install 'promotional' signage (double-sided) on the Lower Denmark Road (opposite Hunwick Rd) - pointing in to Torbay trailhead.$250 ea plus installation600
Sub-total
$8,670
Contingency & Project Management 15%
$1,300
Sub-total
$9,970
10% GST
$997
Total (incl. 10% GST)
$10,967

Interpretation Costs

The following table summarises the likely costs for preparation (research, design), manufacturing and installation costs for the interpretation suggested for the trail. The topics for interpretation have been set out in Section 6.7. The 'species identification signs' listed in the table are for placement around the Torbay Nature Trail, while the 'interpretive panels' are for placement at various locations along the proposed rail-trail between Torbay and Elleker (to be decided by the community).


SizeStyleHardware and other costsLabour (installation) costsTotal
Trail-head sign, including map (Torbay)800mm x 600mmEtched anodised aluminium$2,190$60$2,250
Trail-head sign, including map (Elleker)800mm x 600mmEtched anodised aluminium$2,190$60$2,250
Species identification signs (10 of)300mm x 200mmDigital colour$580 ea$60 ea$6,400
5 interpretive panels600mm x 350mmDigital colour$1,730 ea$60 ea$8,950
Sub-total$19,850
10% GST$1,985
Total (incl. 10% GST)$21,835

Summary of Costs (GST exclusive; project management and contingency included)

Section 1: Elleker Hall to Lower Denmark Road crossing (east)$79,425
Section 2: Lower Denmark Road crossing (east) to Wilgie Road$155,687
Section 3: Wilgie Road (to gate)$6,636
Section 4: Wilgie Road (gate) to Lower Denmark Road crossing (west)$137,034
Section 5: Lower Denmark Road crossing (west) to Torbay Hall$9,970
Interpretation Costs$19,850
Total (excluding GST)$408,602

NOTE 1: Fencing prices are general farming fence rates. It is should be noted that fencing is an issue that requires resolution during the consultation phase if/when trail is to be constructed. This cost can be avoided if decision taken not to re-fence the corridor.

NOTE 2: Bridge re-decking and/or reconstruction cost estimates include an allowance for decking timber and kerbing, abutment repairs, fixings, transport, site works, work in difficult conditions and in elevated situations and a contingency for unforeseen works. Bridges in some locations will need to carry the weight of fire fighting equipment, while in other locations shared use of bridges will require special consideration in the design and upgrading.

NOTE 3: These broad cost estimates are based on contractors' rates. Costs can be considerably reduced through use of in-kind contributions from Council, use of volunteers for various tasks, use of prison crews (for construction tasks), etc.

NOTE 4: These cost estimates are based on recent relevant construction costs from other trail projects. Real-life costs will depend on a number of factors, including the state of the economy, the extent of 'advertising' of construction tenders, the availability and competitiveness of contractors, the rise and fall in materials costs, the choice of materials used in construction and final design details. Tenders submitted by construction contractors may vary significantly from the estimated costs in the tables contained within this report.